This is how the CCGT Ostrołęka power plant is being built
In 2024, the construction site of the gas-steam power plant in Ostrołęka was a place of intense work. Thanks to this, by 2025, the investment has reached a high level of advancement. This applies not only to construction work but also to design and procurement-logistics processes.
business power engineering news01 february 2025 | 09:33 | Source: Energa / Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. Energa
Construction progress of the CCGT Power Plant in Ostrołęka
The combined cycle gas turbine (CCGT) power plant in Ostrołęka is a massive and complex investment and logistical undertaking, which was particularly evident in the past year. As Energa reports, key components and equipment were regularly delivered to the construction site, including the gas turbine, which arrived in early 2024 and was assembled by mid-year. Other transported elements included block transformers—responsible for increasing the generator's output voltage to a level suitable for electricity transmission—and the lubrication system for the plant's turbine set.
Major milestones achieved in 2024
- Successful assembly of the entire turbine set, including the gas and steam turbines along with the generator.
- Installation of the heat recovery steam generator and cooling water pumps.
- Completion of the gasification process for the nearly 28 km-long gas pipeline, which will supply the CCGT unit with natural gas from the Poland-Lithuania interconnector.
- The gas pipeline also received operating permits in both voivodeships it passes through (Podlaskie and Mazowieckie).
Key developments in 2025
The upcoming year will continue to see intense activity at the construction site. The final buildings of the power plant complex will be completed, enabling the installation of auxiliary systems, such as water and gas treatment stations.
- First Half of 2025: Pressure tests of key systems, including the heat recovery steam generator.
- Second Half of 2025: Equipment testing, including the critical "first ignition" of the gas turbine and synchronization with the National Power System.
Balancing energy supply and ensuring security
Ensuring energy security during the energy transition requires generation sources capable of balancing the National Power System as conventional, high-emission assets are phased out. In Poland, CCGT power plants serve as an interim solution. They offer high operational flexibility and produce half the emissions of coal-fired units. This makes them both more environmentally friendly and capable of responding quickly to fluctuations in electricity demand. Moreover, with proper modernization, these plants could use alternative fuels such as biomethane or hydrogen in the future.
Kamil Kusier
redaktor naczelny
gallery
comments
Add the first comment
see also
Austal partners with Damen for local construction of LST 100 for Australian Army
The submarine contract of the decade? Canada weighs South Korea against Germany
Bechtel signs contract with Doraco for Poland’s first nuclear power plant
When two powers clash, Poland must be ready to act. Military security must be the priority
MON, Arka Gdynia and AMW sign letter of intent supporting "Green Industrial District - Kashubia" project
Mine countermeasure vessel Jaskółka begins sea acceptance trials
PEJ relocates headquarters to Pomerania. A strategic step in Poland’s nuclear power development
Radmor hosts delegation from the Republic of Turkey. Advancing maritime security cooperation
3D-printed catamaran: robotic manufacturing sets course for the future of small craft
Navantia and Fincantieri deepen cooperation on the european patrol corvette programme
ADVERTISEMENT
ADVERTISEMENT