Baltica 2 offshore wind farm reaches key milestone with first transformer installation
The Baltica 2 offshore wind farm, a joint venture between PGE and Ørsted, has reached a major milestone with the installation of the first 225 MVA transformer on one of its four offshore substations. This marks a significant step forward in the production and assembly of key components for what will become Poland’s largest offshore wind farm, with a total capacity of 1.5 GW.
business power engineering maritime economy offshore pomerania news24 october 2025 | 07:16 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. Orsted
Offshore substations – the heart of the wind farm
Each of the four offshore substations will serve as the central hub for collecting and transmitting the electricity generated by 107 wind turbines located approximately 40 kilometers off the Polish coast.
Each substation is an impressive five-level structure, measuring 45 x 25 x 20 meters and weighing around 3,000 tonnes. Designed for unmanned operation, the platforms will only be visited by maintenance crews when necessary for inspections and repairs.
- An offshore substation is the heart of a wind farm. These massive structures are crucial for ensuring efficient transmission of offshore wind power. The installation of the first transformer is a symbolic moment that demonstrates production progress in line with schedule and the highest safety standards, said Ulrik Lange, managing director of the Baltica 2 project at Ørsted.
Project progressing towards offshore construction
- Advancing to the next stage of substation production clearly reflects the maturity of the Baltica 2 project. We are entering the final phase of preparation before offshore construction begins. The work on these substations is a great example of international cooperation, which is typical for the global offshore wind industry, said Bartosz Fedurek, CEO of PGE Baltica.
The offshore substations are being delivered under a contract between Ørsted, PGE, and the consortium of SEMCO Maritime and PTSC Mechanical & Construction. The contract covers the design, fabrication, and commissioning of all four substations.
Polish engineering company PROTEA SA will supply specialized cranes for the substations, further emphasizing domestic industry participation in this international project.
Safety and precision at the core of operations
The achievement follows 3.3 million work hours without a lost-time incident, as well as 22 critical heavy lifts carried out safely and precisely on the upper decks. Two of the substations are already structurally complete, while the assembly of the remaining two is progressing on schedule.
The entire offshore transmission system for Baltica 2 is expected to be ready for commissioning in 2027, aligning with the planned start of operations for the wind farm.
Powering 2.5 million homes with green energy
Once operational, Baltica 2 will deliver up to 1.5 GW of clean electricity, enough to power approximately 2.5 million households. As the largest offshore wind project in Poland, it will play a pivotal role in advancing the country’s energy transition and strengthening its renewable energy portfolio in the Baltic Sea.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
gallery
comments
Add the first comment
see also
Crist has started Huragan's bow. The third Miecznik frigate is being built in two Gdynia yards at once
WB Group and Kongsberg to build unmanned maritime systems in Gdynia. Radmor grows to 2,000 jobs
76 turbines stand in the Baltic. Baltic Power completes its offshore campaign and enters commissioning
A 1,112-metre pier into the sea at Lubiatowo has its environmental decision. Reactor vessels will arrive by sea
A third companion for Leviathan. Indratus, the former Game Changer, leaves Oceanco after a refit
Italy uses its 95-year-old tall ship to promote the nation. Poland has Dar Młodzieży and a quarrel over a quay
President signs the fuel windfall tax and demands cuts now. What it means for fishermen and ports
One bid for Gdynia's Outer Port. MSC wants the 5-billion-zloty terminal, three rivals walked away
Batavia goes ashore. The Dutch show what to do with a ship no longer worth keeping afloat
Gdańsk and New York sign a letter of intent. US trade is growing, a direct service is missing
ADVERTISEMENT
ADVERTISEMENT