Shipbuilding industry is awesome. Marcin Ryngwelski on designing & installing sanitary cabins onboard
Sanitary cabins are among the most frequently used spaces on every vessel, yet their integration is one of the more sensitive stages of production. Their placement influences compartment layout, system routing and the build schedule. Marcin Ryngwelski, CEO of PGZ Naval Shipyard, explains how sanitary cabins are planned and installed, and why delays in their delivery can have structural and logistical consequences.
business education maritime economy work at mare shipbuilding industry shipbuilding industry is awesome equipment and technology news13 november 2025 | 09:38 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. Marcin Ryngwelski / PGZ Stocznia Wojenna
Function and configuration
A sanitary cabin is a self-contained unit assigned to a crew or passenger cabin, typically including a toilet and shower. Its size and level of outfitting depend on the vessel’s function and the owner’s specification.
- A passenger ship will have a different standard than a naval vessel. Requirements for number of crew, privacy, durability and ease of maintenance define the final configuration, says Ryngwelski.
Placement defined at the design stage
The arrangement of crew and passenger accommodations, including sanitary cabins, is determined during the technical design phase. This planning must meet regulatory requirements, including corridor width, escape routes and compartment division.
- The shipyard and its design office plan the layout according to capacity requirements provided by the client. The design must ensure compliance with class rules and naval standards. This is not something that can be corrected late in the process, Ryngwelski notes.
Delivery timing is critical
Cabins or their foundations must arrive while the hull or superstructure is still open and accessible.
- The hull must have technological openings that allow these units to be moved inside. If the cabin is delivered too late, and heavy doors or portholes are already installed, the shipyard faces unnecessary rework, explains Ryngwelski.
In cases where the supplier delays delivery, alternative transport paths may need to be created. This can require removal of elements already fitted, extending the schedule and increasing cost.
Assembly process
One common installation method includes:
- marking the position on the deck,
- attaching the cabin base to the deck structure,
- applying the leveling layer or using the factory-finished flooring,
- assembling the cabin walls and internal partitions,
- installing sanitary equipment,
- connecting water supply, drainage and electrical power,
- fitting the cabin door.
- Tolerance and alignment matter—cabin floors must drain correctly, walls must align with bulkheads, and pipe routing must not introduce stress into the system, Ryngwelski emphasizes.
Large passenger ship approach
On large ferries and passenger vessels, where cabin counts may exceed one thousand, the process is different. Fully outfitted cabin modules are produced off-site and installed as entire units.
- They are moved into the vessel in a single operation, once the structure reaches the correct stage. This is a highly coordinated logistics procedure.
First users
During sea acceptance trials, sanitary cabins are first used by:
- shipyard personnel,
- representatives of the owner or navy,
- classification society surveyors,
- regional naval inspectors (for military vessels).
SAT confirms not only the performance of ship systems but also the functionality and durability of outfitting components.
Sanitary cabins appear to be simple interior spaces, yet their integration is tightly linked to design decisions, supply-chain reliability and outfitting sequencing. They represent a precise interface between structural work, piping systems and accommodation standards.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
comments
Add the first comment
see also
February in Szczecin’s shiprepair sector. Ice, overhauls and North Sea expansion
Advanced ROV trials conducted at CTO to validate subsea technologies for offshore applications
University of Gdańsk and PGZ Naval Shipyard join forces for innovation and security
Stadt Naval to deliver electric propulsion system for Polish rescue vessel Ratownik
Gdańsk port’s Basen Górniczy to gain modern port infrastructure
First month of Jantar Unity operations. Polsca ferry paves the way for Batory program units
Baltic Power completes installation of all 78 offshore wind farm foundations
Hapag-Lloyd to acquire ZIM for $4.2bn: strategic consolidation in the container shipping market
Baltica 2 cable corridor taking shape: 150 km of inter-array routes completed in the Baltic Sea
PGE Baltica opens 2026 procurement pipeline to the market. Supplier webinar on 26 February
ADVERTISEMENT
ADVERTISEMENT