Poland’s first offshore wind farm under construction. Prime minister Donald Tusk visits the Baltic
The construction of Poland’s first offshore wind farm, Baltic Power, is progressing in the Baltic Sea. The project is being developed by Orlen Group in partnership with Canada’s Northland Power. Located 23 km off the coast between Łeba and Choczewo, the 1.2 GW installation is scheduled for completion in 2026. Once operational, it will supply clean electricity to over 1.5 million households – covering around 3% of the country’s annual demand.
business power engineering maritime economy investments politics news09 august 2025 | 16:03 | Source: Gazeta Morska | Prepared by: Oskar Wojciechowski | Print

fot. KPRM
During his visit to the Baltic Power service port, prime minister Donald Tusk called the investment – a milestone in Poland’s energy transformation – and emphasised its strategic importance:
– This is Poland’s great opening to the Baltic. The slogan that the Baltic is truly becoming our Polish sea finds its expression in these energy investments – said Donald Tusk.
Largest turbines in Europe
The wind farm will feature 76 offshore turbines with a unit capacity of 15 MW – the largest ever installed in Europe. With rotor blades 115 metres long and total height including foundation reaching 250 metres, these turbines will generate approximately 4 TWh annually, reducing CO₂ emissions by an estimated 2.8 million tonnes per year.
Part of the nacelles are being manufactured at the new Vestas factory in Szczecin, which employs several hundred people. Polish shipyards, cable producers, installation and logistics companies from across the country are also involved in the project.
– We will have some of the largest and most advanced offshore wind farms in Europe and globally. This is the next stage of our major project – we build, we don’t just talk – ensuring Poland’s energy security in line with modern standards – said the prime minister.
Supporting infrastructure and long-term operation
A new onshore substation is being built in Choczewo, while a dedicated service base in Łeba – completed in April 2025 – will operate for at least 30 years. The farm’s total area will cover 130 km², roughly the size of the city of Gdynia.
Future offshore expansion
Baltic Power is the first offshore wind project in Poland to reach the construction phase, but not the last. Orlen Group plans further offshore investments with a combined capacity of around 5.5 GW. The share of Polish companies in future projects is expected to rise to 45%.
– We are making sure Polish companies are increasingly involved – from servicing to subcontracting – so they can benefit from these projects – noted Donald Tusk.
Energy security and regional stability
The prime minister highlighted the geopolitical dimension of offshore wind development, noting its role in reducing dependence on external energy suppliers:
– For many years, Poland’s strategy to move away from Russian energy resources is now bringing results. This giant investment brings us closer to full energy security and independence – said Donald Tusk.
Tusk also addressed concerns about GPS signal disruptions affecting maritime and aviation operations in the region, stating that Poland – currently holding the presidency of the Council of the Baltic Sea States – will convene a summit to coordinate efforts for protecting offshore infrastructure and ensuring regional security.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Oskar Wojciechowski
użytkownik
comments
Add the first comment
see also
A 1,112-metre pier into the sea at Lubiatowo has its environmental decision. Reactor vessels will arrive by sea
A third companion for Leviathan. Indratus, the former Game Changer, leaves Oceanco after a refit
Italy uses its 95-year-old tall ship to promote the nation. Poland has Dar Młodzieży and a quarrel over a quay
President signs the fuel windfall tax and demands cuts now. What it means for fishermen and ports
One bid for Gdynia's Outer Port. MSC wants the 5-billion-zloty terminal, three rivals walked away
Batavia goes ashore. The Dutch show what to do with a ship no longer worth keeping afloat
Gdańsk and New York sign a letter of intent. US trade is growing, a direct service is missing
A 240 million zloty dock and a new chief executive. Gryfia begins its modernisation programme
From one million to 38.6 million tonnes. Naftoport turns 35 and builds a berth for the largest tankers
Fake invoices worth 16 million zloty and 284 foreign workers. Suspect brought from Spain to Gdańsk
ADVERTISEMENT
ADVERTISEMENT