Warsaw court to rule on environmental challenge to Świnoujście container terminal
On Monday, the Provincial Administrative Court (WSA) in Warsaw is expected to issue a ruling on the environmental permit for the planned deepwater container terminal in Świnoujście. The case stems from a joint legal challenge filed by German and Polish environmental organizations, raising concerns about the project’s ecological impact on the southern Baltic coast.
business maritime economy investments logistics west pomerania ports transport and forwarding news04 august 2025 | 09:22 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

Wizualizacja terminala kontenerowego w Świnoujściu / fot. Ministerstwo Infrastruktury
The court had previously suspended the enforceability of the environmental decision issued in February 2025 by Poland’s General Directorate for Environmental Protection (GDOŚ), citing the complexity of the matter. The final hearing took place on July 21, with the court announcing that a verdict would be issued after further deliberation.
The investment—led by the Szczecin and Świnoujście Seaports Authority and coordinated by Poland’s Ministry of Infrastructure—is considered one of the country’s most ambitious maritime infrastructure projects. The terminal is designed to handle two 400-meter-long transoceanic vessels simultaneously and is scheduled for completion by 2029. The port infrastructure alone is expected to cost around PLN 10 billion (approx. €2.3 billion), with the overall project reaching PLN 12.5 billion.
The complaint was filed by the German NGO Bürgerinitiative Lebensraum Vorpommern (BLV), based on the island of Usedom, and the Polish group Zielone Wyspy Świnoujście. Both allege that the environmental impact assessment failed to fully account for cross-border risks, including to Natura 2000 areas and marine habitats. German media have highlighted support for the complaint from local authorities in nearby Heringsdorf, though the municipality is not a formal party to the proceedings.
Deputy Infrastructure Minister Arkadiusz Marchewka has dismissed the objections, describing them as “absurd” and politically motivated.
- We are aware that we are dealing with opponents of port development, he said, referencing German press coverage that frames Świnoujście as a competitive threat to ports on the German Baltic coast.
Marchewka emphasized that the court’s suspension affects only the enforceability of the environmental permit—not the investment itself. Preparatory works, including seabed magnetic surveys, soil investigations, and approach channel design, have already been completed. Groundbreaking for the terminal’s access infrastructure is scheduled for late 2025.
The government views the terminal as vital to its long-term goal of tripling national container throughput to 10 million TEU by 2030. In 2024, Polish ports handled 3.3 million TEU, generating PLN 56 billion in customs and tax revenue.
Should the court annul the permit, the decision can be appealed to the Supreme Administrative Court (NSA) within 30 days. A third possibility—requiring the investor to supplement documentation—has also been raised as a likely outcome.
Despite legal hurdles, the Ministry of Infrastructure remains firm: the Świnoujście container terminal is going ahead. A new 65-kilometer, 17-meter-deep fairway will link the terminal to international shipping routes. Construction will be carried out by a Qatari-Belgian consortium.
- This is a strategic project, said Marchewka. - It’s not a matter of if—it’s a matter of when.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
comments
Add the first comment
see also
Navantia and Fincantieri deepen cooperation on the european patrol corvette programme
Galeon Yachts and Meyer Shank Racing: merging luxury yachts with motorsport expertise
Unmanned systems and naval firepower modules. WB Group showcases integrated capabilities at Enforce Tac 2026
Swedish ports record lowest ship calls in 18 years. Implications for the maritime sector
February in Szczecin’s shiprepair sector. Ice, overhauls and North Sea expansion
Advanced ROV trials conducted at CTO to validate subsea technologies for offshore applications
University of Gdańsk and PGZ Naval Shipyard join forces for innovation and security
Stadt Naval to deliver electric propulsion system for Polish rescue vessel Ratownik
Gdańsk port’s Basen Górniczy to gain modern port infrastructure
First month of Jantar Unity operations. Polsca ferry paves the way for Batory program units
ADVERTISEMENT
ADVERTISEMENT