Port of Gdańsk’s T5 terminal advances as key installation hub for Baltica 2 offshore wind project
Construction works at the T5 installation terminal in the Port of Gdańsk have reached another major milestone, marking steady progress of one of the most important offshore wind infrastructure projects in the Baltic Sea region. The terminal is being developed by Istrana to support the Baltica 2 offshore wind farm.
business power engineering maritime economy investments offshore ports news04 february 2026 | 07:02 | Source: Gazeta Morska | Prepared by: Oskar Wojciechowski | Print

fot. PGE Baltica
Representatives of Ørsted and PGE visited the construction site to review progress and discuss upcoming project milestones. Once completed, the T5 terminal will serve as a logistics base for storage, pre-assembly and installation of offshore wind turbine components.
The Port of Gdańsk will act as the main installation port for 107 wind turbines forming part of the Baltica 2 project, with offshore installation scheduled to begin in 2027. Timely delivery of the installation terminal is considered a critical success factor for the overall offshore campaign.
The T5 terminal is expected to operate as a dedicated offshore wind facility for at least 10–15 years. After this period, its future use will depend on evolving market needs. The on-schedule execution of the project by Polish contractor Istrana underlines the growing capabilities of the domestic port and construction sector in delivering large-scale offshore infrastructure.
For Istrana, T5 represents a strategic investment reinforcing the Port of Gdańsk’s position as a key logistics hub for offshore wind development in the Baltic Sea. The scale and complexity of the works highlight the long-term importance of the terminal both for the Baltica 2 project and for the port’s future role in offshore energy.
Upcoming construction phases include continued reinforced concrete and piling works, development of working platforms, delivery of prefabricated elements and commencement of network infrastructure installations. In parallel, final ground levelling and soil strengthening works will be completed to prepare the terminal for heavy offshore components handling.
The lease agreement for the port area designated for the T5 terminal was signed in 2024 by PGE, Ørsted and Istrana. Covering more than 21 hectares, the terminal has been designed to accommodate both jack-up installation vessels and ro-ro transport units simultaneously, significantly enhancing offshore installation capabilities in Gdańsk.
With a total capacity of 1.5 GW, Baltica 2 will become the largest offshore wind farm in the Baltic Sea, supplying clean renewable energy to approximately 2.5 million households. The project is partially financed through Poland’s National Recovery Plan, with PLN 5.5 billion allocated to PGE’s share, while Ørsted is funding its part from own resources.
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Oskar Wojciechowski
redaktor
comments
Add the first comment
see also
February in Szczecin’s shiprepair sector. Ice, overhauls and North Sea expansion
Advanced ROV trials conducted at CTO to validate subsea technologies for offshore applications
University of Gdańsk and PGZ Naval Shipyard join forces for innovation and security
Stadt Naval to deliver electric propulsion system for Polish rescue vessel Ratownik
Gdańsk port’s Basen Górniczy to gain modern port infrastructure
First month of Jantar Unity operations. Polsca ferry paves the way for Batory program units
Baltic Power completes installation of all 78 offshore wind farm foundations
Hapag-Lloyd to acquire ZIM for $4.2bn: strategic consolidation in the container shipping market
Baltica 2 cable corridor taking shape: 150 km of inter-array routes completed in the Baltic Sea
PGE Baltica opens 2026 procurement pipeline to the market. Supplier webinar on 26 February
ADVERTISEMENT
ADVERTISEMENT