BOKA Falcon commences works on the Baltica 2 offshore wind farm
A new stage of seabed preparation has begun for the Baltica 2 offshore wind project, jointly developed by PGE Polska Grupa Energetyczna and Ørsted. The BOKA Falcon, operated by marine engineering company Boskalis, has entered Polish waters to carry out specialized subsea works.
business power engineering maritime economy offshore pomerania18 august 2025 | 10:43 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. Boskalis
The vessel is equipped with two advanced ploughs: T-Rex and Megalodon. The T-Rex will remove dozens of massive boulders located within the planned wind farm area, while the Megalodon will excavate a precision trench for the installation of subsea power cables.
These operations are essential to prepare the seabed for the planned installation, by 2026, of approximately 300 km of export cables and 170 km of inter-array cables. Once completed, Baltica 2 will feature 107 wind turbines with a total capacity of 1.5 GW.
The offshore wind farm will generate clean electricity equivalent to the consumption of around 2.5 million households, playing a pivotal role in Poland’s energy transition and strengthening the country’s energy security.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
gallery
comments
Add the first comment
see also
From Iver Huitfeldt to ORP Wicher. How a Danish frigate design reached a Polish shipyard
Gdańsk secures PLN 16.5 million to expand Górki Zachodnie marina
Szczecin Maritime University launches tender for PLN 625 million research vessel
PGE Baltica signs letter of intent with Chordata. Turbines to get predictive acoustic monitoring
Bechtel takes over Poland's nuclear plant site. Earthworks begin in Choczewo
WB Group moves naval communications from land to sea. FONET-NAVY system reaches more warships
The Maritime Office in Słupsk returns after six years
Thirty years and 26 hectares. Baltic Hub leases Deepwater and plans a second rail siding
Themis nears first flight. The rocket's return manoeuvre is being built in Gdynia
Aquapark Reda after the chemical incident. Sharks, permits and species protection
ADVERTISEMENT
ADVERTISEMENT