Baltica 2 Nears Construction - Seabed Clearance Operations Underway in the Baltic Sea
Ørsted has launched preparatory offshore activities for the Baltica 2 offshore wind farm – the largest project of its kind in Polish waters. The ongoing seabed clearance, including the relocation of boulders and other subsea obstacles, marks a critical milestone ahead of the construction phase.
business power engineering maritime economy offshore pomerania news11 july 2025 | 07:17 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. PGE Baltica
Currently operating in the designated area is the Olympic Electra vessel, which is carrying out boulder relocation along both turbine foundation zones and future export cable routes. The seabed preparation campaign is scheduled to continue through early 2026.
The vessel is equipped with a specialized boulder picking spread supplied by Utility ROV Services (UTROV). This advanced tool enables safe relocation of objects up to 3 meters in diameter, such as boulders, steel wires, lost fishing nets, and timber debris.
– These preparatory works at sea are the final stage before we move into full-scale construction. Boulder relocation directly impacts the safety and efficiency of subsequent phases – including foundation installation and deployment of subsea infrastructure – said Ulrik Lange, Vice President and Project Director of Baltica 2 at Ørsted. – As the offshore EPC lead and a company with over 30 offshore wind farms built worldwide, we’re excited to enter this advanced stage in the Baltic Sea.
According to PGE Baltica’s CEO Bartosz Fedurek, around 10,000 subsea objects are to be relocated during the campaign.
– Baltica 2 is now literally moving offshore. The clearance work paves the way for the installation of foundations and subsea components scheduled for 2026 and 2027. The project involves dozens of crew members, as well as supervision teams and specialists who have been involved since the seabed survey phase – Fedurek noted.
Once completed, the cleared seabed will allow for the deployment of scour protection systems and turbine foundations in 2026, followed by internal array cables and export cables in 2027.
The contract with UTROV was signed in 2025. The boulder relocation technology has already been successfully used in similar offshore operations across Europe.
Baltica 2 – A Milestone for Poland’s Offshore Wind Industry
Baltica 2, jointly developed by Ørsted and PGE, is poised to become Poland’s largest offshore wind farm with an installed capacity of up to 1.5 GW. Scheduled for commissioning in 2027, it will be capable of supplying green electricity to approximately 2.5 million Polish households. The project represents a major leap in the country’s transition toward renewable energy and sustainable power generation.
see also
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
gallery
comments
Add the first comment
see also
February in Szczecin’s shiprepair sector. Ice, overhauls and North Sea expansion
Advanced ROV trials conducted at CTO to validate subsea technologies for offshore applications
University of Gdańsk and PGZ Naval Shipyard join forces for innovation and security
Stadt Naval to deliver electric propulsion system for Polish rescue vessel Ratownik
Gdańsk port’s Basen Górniczy to gain modern port infrastructure
First month of Jantar Unity operations. Polsca ferry paves the way for Batory program units
Baltic Power completes installation of all 78 offshore wind farm foundations
Hapag-Lloyd to acquire ZIM for $4.2bn: strategic consolidation in the container shipping market
Baltica 2 cable corridor taking shape: 150 km of inter-array routes completed in the Baltic Sea
PGE Baltica opens 2026 procurement pipeline to the market. Supplier webinar on 26 February
ADVERTISEMENT
ADVERTISEMENT