Szczecin Shipyard “Wulkan” begins construction of new buoy tender for the Maritime Office in Szczecin

A steel-cutting ceremony was held today at Szczecin Shipyard “Wulkan”, marking the official start of construction of a new buoy tender for the Maritime Office in Szczecin. The traditional event, involving the cutting of the first steel plates for the vessel’s hull, formally inaugurates the building process.

Rendering of the blue and white buoy tender SE-114 on water near shipyard cranes
fot. Urząd Morski w Szczecinie

In brief

The Wulkan shipyard in Szczecin has begun construction of a buoy tender for the Maritime Office in Szczecin with a first steel cutting ceremony. The contract signed in April this year is worth more than PLN 30 million, and the vessel is to be built within 18 months. The buoy tender, 29 metres long, 8.30 metres wide, with a speed of 10 knots and ice class L1, will deploy and retrieve buoys and maintain fixed navigation marks, with the possibility of taking part in icebreaking operations. Arkadiusz Marchewka, Secretary of State at the Ministry of Infrastructure, attended the event.

The ceremony was attended by Arkadiusz Marchewka, Secretary of State at the Ministry of Infrastructure.

The contract for the project was signed in April this year, with a value exceeding PLN 30 million. The delivery schedule foresees completion within 18 months.

The new buoy tender will serve the maintenance and management of navigational aids within the jurisdiction of the Maritime Office in Szczecin, covering both ports and fairways. Its operational scope will include deploying and retrieving buoys, as well as maintaining permanent floating aids such as beacons and dolphins. In addition, the vessel will be capable of supporting icebreaking operations.

Key technical parameters of the vessel:

  • overall length: 29 m
  • overall beam: 8.30 m
  • height to main deck: 2.70 m
  • design draft: 1.80 m
  • construction draft: 2.20 m
  • service speed: 10 knots
  • ice class: L1

The addition of this modern buoy tender will significantly enhance the operational capacity of the Maritime Office in Szczecin and further improve navigational safety in the region.

Source: Gazeta Morska · Compiled by: Kamil Kusier

Kamil Kusier executive editor All articles by this author →

Comments (0)

The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.

Nobody has commented on this article yet.

Add a comment

0 comments

Related articles