Rewa strengthens coastal protection as second stage of flood-defence works progresses
The second stage of a key coastal protection project is underway in Rewa, within the Kosakowo municipality, led by the Maritime Office in Gdynia. The works form part of the long-term programme “Shoreline Flood Protection from the Waters of the Gulf of Gdańsk”, focused on safeguarding the Baltic coastline from storm surges and flooding.
In brief
The Maritime Office in Gdynia is carrying out the second stage of a flood protection project worth about PLN 7 million in Rewa, Kosakowo municipality. A new 480-metre seawall, to be sheltered by a dune and forming the base of a seaside promenade, is under construction, and the existing 420-metre structure has been renovated. By the end of October about 50 running metres of the new retaining wall were built and tubular pile driving was completed. The second stage is due in February 2026, with finishing works in autumn 2026, and the National Fund for Environmental Protection and Water Management co-finances the project.
New coastal revetment to support future seaside promenade
The current stage includes the construction of a 480-metre coastal revetment that will later be reinforced with a dune system. The previously existing 420-metre section has already been modernised. Beyond its protective function, the new revetment will provide the structural base for an almost half-kilometre seaside promenade, improving public access and enhancing the local tourism infrastructure.
All heavy works are scheduled outside the peak summer season to minimise disruption to visitors.
Expanded flood-defence infrastructure for the Baltic shoreline
As part of the broader investment, flood-response capabilities are being strengthened. In nearby Mechelinki, two specialised containers have been positioned and equipped with:
- inflatable flood barriers with pumping systems,
- a floating pump,
- a lighting mast with generator,
- a transport trolley for flood-control equipment,
- sandbags and auxiliary gear.
The containers will store components of the mobile flood-defence system that can be rapidly deployed on the Rewa revetment. These improvements complement earlier works completed in 2023, when wide protective beaches were created in Rewa and Mechelinki to act as natural shock absorbers during storm events.
Construction progress on key shoreline structures
By the end of October, around 50 metres of the new retaining wall had been completed, including gravel-filled mattresses and sections of stone armour. All tubular piles for a future beach access ramp and stairway have also been installed.
Reinforced-concrete works continue toward the cross on the Rewa Spit, and additional retaining-wall segments with integrated mobile-barrier slots will be built in the coming weeks.
Steel structures for the new beach access points are currently being fabricated off-site, with the first installation planned for November. The project remains on schedule, with completion of the second stage expected in February 2026 and finishing works in autumn 2026.
Funding and project framework
The investment is carried out under a contract signed in October 2024, with a value of approximately PLN 7 million. It is co-financed by the National Fund for Environmental Protection and Water Management as part of the “Shoreline Flood Protection from the Waters of the Gulf of Gdańsk” programme.
Source: Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Maritime economy Poland’s constitutional crisis is also a maritime story
Safety and rescue Polish SAR’s new rescue vessel Mistral launched at Kewatec in Finland
Investments Port of Gdańsk opens T5 offshore installation terminal, bringing Baltica 2 logistics home from Bornholm
Maritime economy Bursztyn Unity to raise the Polish flag, but crew terms remain an open question
Energy and offshore Bałtyk 2 and 3 offshore wind: all 100 foundations installed, export cables laid
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.