Port of Gdańsk’s T5 terminal advances as key installation hub for Baltica 2 offshore wind project

Construction works at the T5 installation terminal in the Port of Gdańsk have reached another major milestone, marking steady progress of one of the most important offshore wind infrastructure projects in the Baltic Sea region. The terminal is being developed by Istrana to support the Baltica 2 offshore wind farm.

Snow covered port terminal yard with rows of containers and gantry cranes along the quay
fot. PGE Baltica

In brief

Istrana has completed another stage of construction of the T5 installation terminal in the Port of Gdańsk, intended for the Baltica 2 offshore wind farm. The T5 terminal, covering more than 21 hectares, will simultaneously handle jack-up installation vessels and ro-ro units, and installation of 107 wind turbines is due to start in 2027. The port land lease agreement was signed in 2024 by PGE, Ørsted and Istrana, and the terminal is to serve offshore wind energy for at least 10 to 15 years. Baltica 2, with a capacity of 1.5 GW, is to supply around 2.5 million households, with PLN 5.5 billion coming from the National Recovery Plan.

Representatives of Ørsted and PGE visited the construction site to review progress and discuss upcoming project milestones. Once completed, the T5 terminal will serve as a logistics base for storage, pre-assembly and installation of offshore wind turbine components.

The Port of Gdańsk will act as the main installation port for 107 wind turbines forming part of the Baltica 2 project, with offshore installation scheduled to begin in 2027. Timely delivery of the installation terminal is considered a critical success factor for the overall offshore campaign.

The T5 terminal is expected to operate as a dedicated offshore wind facility for at least 10–15 years. After this period, its future use will depend on evolving market needs. The on-schedule execution of the project by Polish contractor Istrana underlines the growing capabilities of the domestic port and construction sector in delivering large-scale offshore infrastructure.

For Istrana, T5 represents a strategic investment reinforcing the Port of Gdańsk’s position as a key logistics hub for offshore wind development in the Baltic Sea. The scale and complexity of the works highlight the long-term importance of the terminal both for the Baltica 2 project and for the port’s future role in offshore energy.

Upcoming construction phases include continued reinforced concrete and piling works, development of working platforms, delivery of prefabricated elements and commencement of network infrastructure installations. In parallel, final ground levelling and soil strengthening works will be completed to prepare the terminal for heavy offshore components handling.

The lease agreement for the port area designated for the T5 terminal was signed in 2024 by PGE, Ørsted and Istrana. Covering more than 21 hectares, the terminal has been designed to accommodate both jack-up installation vessels and ro-ro transport units simultaneously, significantly enhancing offshore installation capabilities in Gdańsk.

With a total capacity of 1.5 GW, Baltica 2 will become the largest offshore wind farm in the Baltic Sea, supplying clean renewable energy to approximately 2.5 million households. The project is partially financed through Poland’s National Recovery Plan, with PLN 5.5 billion allocated to PGE’s share, while Ørsted is funding its part from own resources.

Source: Gazeta Morska · Compiled by: Oskar Wojciechowski

Oskar Wojciechowski sales / advertising All articles by this author →

Comments (0)

The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.

Nobody has commented on this article yet.

Add a comment

0 comments

Related articles