Poland’s offshore wind accelerates as projects enter execution phase
Poland’s offshore wind sector is moving decisively into the execution phase, with visible progress across both offshore and onshore infrastructure. Recent developments point not only to the rapid advancement of key projects, but also to the growing role of Polish companies within the European supply chain.
In brief
PGE Baltica CEO Bartosz Fedurek announced that construction of the onshore substation for the Baltica 2 project is almost complete and most of the technological components are already on site. The sea to shore connection is practically ready, which means the Baltica 2 project is moving from the construction phase to operational preparations. Bartosz Fedurek indicated that talks during WindEurope Annual Event 2024 confirmed the presence of Polish offshore in the European ecosystem, and the participation of domestic industry, Local Content, was one of the main topics of the European Economic Congress.
According to Bartosz Fedurek of PGE Baltica, the pace of activity has intensified significantly in recent weeks, reflecting a broader shift from planning to delivery.
Baltica 2 nearing infrastructure completion
One of the most advanced projects in Poland’s offshore pipeline is Baltica 2, developed by PGE Baltica. The onshore substation is close to completion, with most key components already installed and final construction works nearing completion.
At the same time, the offshore-to-onshore connection infrastructure is at a very advanced stage, indicating that the project is approaching operational readiness. This marks a critical milestone as Poland prepares for large-scale offshore wind generation.
Poland strengthens its role in Europe
Poland’s growing position in the sector was also evident during WindEurope Annual Event 2024, where industry representatives discussed market developments and future outlook.
The country is increasingly visible both as an investment destination and as a supplier base. Polish companies are gaining recognition across Europe and are becoming more active participants in international supply chains.
Energy security drives investment
Geopolitical tensions continue to underline the importance of energy independence across Europe. As a result, renewable energy sources are gaining even stronger strategic relevance.
At the same time, analyses indicate that systems based on wind and solar power can offer lower long-term system costs compared to continued reliance on fossil fuels. This economic rationale is reinforcing the pace of the energy transition.
Local Content becomes a key factor
The importance of domestic industrial participation was also highlighted during the European Economic Congress.
Local content is increasingly seen as essential for the sustainable development of offshore wind in Poland, both in terms of economic impact and long-term sector stability. Discussions also included comparisons between offshore wind and other low-carbon technologies, including nuclear energy.
A strategic sector with growing demands
The rapid growth of the offshore wind sector brings clear benefits, but also increasing demands on those involved in its development. High levels of project intensity often translate into limited time and energy beyond professional responsibilities, highlighting the human aspect behind large-scale infrastructure projects.
With projects such as Baltica 2 approaching key milestones and supply chains continuing to develop, Poland is strengthening its position within the European offshore wind market.
The coming months will be crucial in maintaining momentum, particularly in terms of project execution, grid integration, and the effective delivery of local content commitments.
Source: Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Equipment and technology WB Group takes Polish drones from Tokyo to SOFEX in Jordan in a single week
Ports and logistics PGE books Gdańsk’s T5 terminal for the long haul: Baltica 2 first, then more offshore wind farms
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.