Milestone achieved at Sofia offshore wind farm - Van Oord completes foundation installation
Dutch engineering company Van Oord has successfully completed the installation of all monopile foundations at the Sofia Offshore Wind Farm. This critical phase was carried out using the specialized offshore installation vessel Aeolus, operating at Dogger Bank in the central North Sea.
In brief
Van Oord has completed installation of all foundation monopiles at the Sofia Offshore Wind Farm, using the installation vessel Aeolus operating on Dogger Bank in the central North Sea. The Sofia farm, with a target capacity of 1.4 GW, is to supply energy to around 1.2 million households in the United Kingdom after commissioning in 2026. Van Oord is also laying and burying more than 360 kilometres of inter-array cables connecting the turbines to the offshore substations.
The 1.4 GW Sofia Offshore Wind Farm, scheduled to become operational in 2026, will supply clean renewable energy to approximately 1.2 million UK households. As one of the largest offshore wind projects in Europe, Sofia demonstrates the rapid growth of large-scale renewable infrastructure in the North Sea region.
In addition to foundation installation, Van Oord is also progressing with the installation and burial of over 360 kilometers of array cables, connecting turbines to offshore substations. The work is being conducted according to strict engineering and environmental standards, ensuring safe and efficient project delivery.
Van Oord is a global leader in offshore wind, dredging, and coastal engineering, headquartered in Rotterdam. Its modern fleet includes installation vessels, dredgers, and cable-laying ships. The company’s involvement in the Sofia project underscores its pivotal role in the global energy transition and the sustainable development of maritime industries.
Source: Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Equipment and technology WB Group takes Polish drones from Tokyo to SOFEX in Jordan in a single week
Ports and logistics PGE books Gdańsk’s T5 terminal for the long haul: Baltica 2 first, then more offshore wind farms
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.