Crist has started Huragan's bow. The third Miecznik frigate is being built in two Gdynia yards at once
Weeks before the November keel laying of Huragan, the third frigate of the Miecznik programme, the Crist shipyard in Gdynia began cutting steel for her bow block on 5 October. The finished section will travel along the port channel to the neighbouring PGZ Stocznia Wojenna and be joined to the hull that has been taking shape there since April. Crist is building sections for all three frigates, and the proximity of the two yards in the port of Gdynia, as both write, eases logistics and coordination.
In brief
The Crist shipyard in Gdynia began cutting steel on 5 October for the bow block of Huragan, the third frigate of the Miecznik programme. The finished bow block will travel along the port canal to PGZ Stocznia Wojenna, where the Huragan hull has been under construction since April and the keel will be laid in November. Delivery of Huragan is planned for 2031, and of the first frigate, Wicher, for 2029. The Miecznik programme frigates displace about 7000 tonnes.
This is not news about a single steel block but about the model in which Polish naval shipbuilding now builds its ships: one yard integrates, others deliver sections, and the port channel replaces the motorway.
Three frigates at three stages
The Miecznik programme comprises three multi-role frigates of around 7,000 tonnes, built at PGZ Stocznia Wojenna to Babcock's Arrowhead 140 design. The first, Wicher, launched on 12 August, is being fitted out at the quay and is due to be delivered to the navy in 2029. The second, Burza, after her keel laying in December 2025, is at the section-building stage in the hall vacated by Wicher, with launch planned for the turn of 2027 and 2028. The third, Huragan, began in April with steel cutting, and her keel will be laid in November; delivery is planned for 2031.
The naval yard calls the programme the largest in the history of the Polish Navy and is working on the three sister ships in parallel, a situation without precedent in Polish shipbuilding for decades. Huragan's bow at Crist means that elements of all three frigates are now physically under construction in Gdynia at the same time.
- We have begun building the bow block for the third frigate of the Miecznik programme. It is the next stage of our participation in the largest shipbuilding programme in the history of the Polish Navy. We are proud to add our brick to each of these ships - the Crist yard wrote in its statement.
Crist, a private yard in a state programme
Crist is a privately owned yard that for years has built in Gdynia mainly for the offshore market: vessels for the construction and servicing of wind farms, specialised ships, hulls for yards in Western Europe. In September we wrote about its results against the European shipyard field, which showed the company to be among the few in Poland able to build large and complex structures for export. Participation in Miecznik is something different for it: work for the Polish Navy, to British documentation, to a warship standard that differs from the civilian one in welding, inspection and acceptance.
For PGZ Stocznia Wojenna, Crist is the partner that keeps the rhythm going. The hull hall at the naval yard holds one hull at a time: Wicher left it in August, Burza took it over the same month, Huragan will follow. When sections are built in parallel next door, the hull in the hall is assembled from finished blocks rather than built from plate, and that is the difference between six years for a prototype and the five years for a series ship that the yard promises.
A model Gdynia is testing on two programmes
The naval yard applies the same scheme to Ratownik, the rescue ship whose bow block the Szczecin yard Wulkan has been building since May; there the section will come from West Pomerania, here it will float across the port. In both cases Gdynia is the integrator responsible for the whole, and partners deliver finished parts of the hull. In Europe that is the norm: the Type 26 frigates for the Royal Navy are assembled from blocks from several yards, and Germany's F126 joins plants in Wolgast, Kiel and Hamburg. In Poland the model is new, and Miecznik is its first test at scale.
The benefit goes beyond the schedule. Every yard that builds a section of a warship gains certifications, procedures and people it did not have, and with them can bid for the next programmes, its own or others'. After three frigates Crist will hold a reference no other private yard in Poland has, and Wulkan after Ratownik its first naval work in years. Gdynia, where two yards are separated by a channel and the third, Nauta, by a few hundred metres of quay, has everything it takes to be the place where this model takes root.
Huragan's bow is for now cut steel. When the keel of the third frigate is laid in November, three ships of this class will be under construction in Gdynia, something the Polish coast has never seen.
Source: Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Equipment and technology WB Group takes Polish drones from Tokyo to SOFEX in Jordan in a single week
Ports and logistics PGE books Gdańsk’s T5 terminal for the long haul: Baltica 2 first, then more offshore wind farms
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.