Cape Pomerania. New offshore port to rise in Świnoujście
At the gala marking the 75th anniversary of the ports of Szczecin and Świnoujście, Jarosław Siergiej, CEO of Szczecin and Świnoujście Seaports Authority (ZMPSiŚ SA), unveiled the vision of a major infrastructure project: the construction of an offshore port in Świnoujście, with a state-of-the-art container terminal as its first stage. The development, branded Cape Pomerania, will create 186 hectares of new land reclaimed from the sea.
In brief
The Szczecin and Świnoujście Seaports Authority has presented the design of an outer port in Świnoujście named Przylądek Pomerania, which involves reclaiming 186 hectares of new land. The first stage will be a container terminal of about 70 hectares, able to handle ships up to 400 metres long, together with an integrated breakwater; completion is planned for 2029. The project includes a new approach channel to Świnoujście 65 kilometres long and 17 metres deep, and the cost is estimated at over PLN 10 billion. The terminal infrastructure will be built by a consortium of companies from Qatar and Belgium, while the maritime part will be led by the Maritime Office in Szczecin.
Container terminal as the first milestone
According to Infrastructure Minister Arkadiusz Marchewka, the priority is to complete the container terminal, designed to handle the largest transoceanic vessels entering the Baltic – up to 400 meters in length. Around 70 hectares of the newly created land will be allocated for the terminal, while the remainder will be reclaimed using dredged material from fairway deepening works.
– By 2029, we expect to finalize the container terminal and integrated breakwater. That will mark the emergence of a new 186-hectare landmass – a new chapter for Poland’s maritime future – emphasized Minister Marchewka.
New fairway and long-term opportunities
The project also includes a new 65-kilometer-long, 17-meter-deep approach channel to Świnoujście, ensuring accessibility for the world’s largest ocean-going vessels. While the terminal is the immediate focus, Cape Pomerania is envisioned as a long-term growth platform for multiple port-related activities.
– This is not only about one terminal, but about creating room for decades of port development, Marchewka added.
Project partners and scale
The investment is estimated at over PLN 10 billion. The container terminal infrastructure will be developed by a consortium of Qatari and Belgian companies, while the maritime works will be carried out by the Maritime Office in Szczecin.
Cape Pomerania is set to become both a strategic gateway for container traffic and a bold symbol of Poland’s expanding presence in global maritime logistics.
Source: Gazeta Morska / PAP · Compiled by: Kamil Kusier
Related articles
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Equipment and technology WB Group takes Polish drones from Tokyo to SOFEX in Jordan in a single week
Ports and logistics PGE books Gdańsk’s T5 terminal for the long haul: Baltica 2 first, then more offshore wind farms
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.