Baltica 2: horizontal directional drilling underway in Choczewo
Work has begun on a key stage of the Baltica 2 offshore wind farm – the largest project of its kind in Poland, developed jointly by PGE and Ørsted. In the municipality of Choczewo, horizontal directional drilling (HDD) is being used to install export cable ducts beneath the shoreline, connecting offshore infrastructure with the onshore grid in a way that protects both the environment and the coastal landscape.
In brief
Trenchless horizontal directional drilling (HDD) for the Baltica 2 offshore wind farm has started in the Choczewo municipality. Four bores will each be about 1,200 metres long and will run 20 to 30 metres below ground level, without interfering with the beach and dunes. The works are being carried out by a consortium of ROMGOS Gwiazdowscy and ZRB Janicki, and the route was optimised to bypass a smooth snake habitat, the Lubiatowska Dune and Natura 2000 areas. Completion of the drilling is planned for the turn of 2025 and 2026, after which installation of the export cables of the 1.5 GW Baltica 2 farm will begin.
HDD enables trenchless landfall connection
HDD technology allows for highly precise drilling under the surface without the need for open trenching or disruption to dunes and beaches. Each of the four planned boreholes will be approximately 1,200 meters long, at depths of 20–30 meters below ground level. The work is being carried out by a consortium of Polish contractors: ROMGOS Gwiazdowscy and ZRB Janicki.
- This is a symbolic step for the entire project – connecting the offshore section with the onshore infrastructure, said Ulrik Lange, project director for Baltica 2 at Ørsted. - Using HDD, we can do this in a way that is safe for the environment and virtually invisible from the beach.
Bartosz Fedurek, president of PGE Baltica, added: - This is the least invasive way to install export cables. It does not require beach closures and allows us to carry out the work while preserving the landscape and natural surroundings.
Access maintained, local impact minimized
Public access to the beach remains open via marked pedestrian routes. The developers ask that all visitors follow signage and guidance from site personnel. Activities are coordinated closely with local authorities, and any necessary temporary changes to access or traffic will be communicated in advance.
To reduce noise-related inconvenience for residents and tourists, the project uses carefully selected equipment and construction zones located away from residential areas and the beachfront.
Environmental safeguards in place
Before the drilling began, comprehensive environmental studies were carried out both offshore and onshore. As a result, the cable route was designed to avoid ecologically sensitive areas, including habitats of the smooth snake (Coronella austriaca, a protected species in Poland), and the Lubiatowska Dune, one of the region’s most valuable natural features. The design also takes into account Natura 2000 protected areas.
Qualified environmental supervisors will oversee compliance with environmental regulations throughout construction.
Clean power for 2.5 million homes
Once drilling is completed – expected between late 2025 and early 2026 – installation of the export cables will begin. These will carry electricity generated by the offshore turbines to the national grid. With a planned capacity of 1.5 GW, Baltica 2 will provide enough clean, renewable power for around 2.5 million households, making it a cornerstone of Poland’s offshore energy transformation.
Source: Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Equipment and technology WB Group takes Polish drones from Tokyo to SOFEX in Jordan in a single week
Ports and logistics PGE books Gdańsk’s T5 terminal for the long haul: Baltica 2 first, then more offshore wind farms
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.