Skip to content
Partners

Baltica 2: horizontal directional drilling underway in Choczewo

Work has begun on a key stage of the Baltica 2 offshore wind farm – the largest project of its kind in Poland, developed jointly by PGE and Ørsted. In the municipality of Choczewo, horizontal directional drilling (HDD) is being used to install export cable ducts beneath the shoreline, connecting offshore infrastructure with the onshore grid in a way that protects both the environment and the coastal landscape.

Aerial view of a construction site with a crane, containers and drill pipes amid coastal forest
fot. Orsted

In brief

Trenchless horizontal directional drilling (HDD) for the Baltica 2 offshore wind farm has started in the Choczewo municipality. Four bores will each be about 1,200 metres long and will run 20 to 30 metres below ground level, without interfering with the beach and dunes. The works are being carried out by a consortium of ROMGOS Gwiazdowscy and ZRB Janicki, and the route was optimised to bypass a smooth snake habitat, the Lubiatowska Dune and Natura 2000 areas. Completion of the drilling is planned for the turn of 2025 and 2026, after which installation of the export cables of the 1.5 GW Baltica 2 farm will begin.

HDD enables trenchless landfall connection

HDD technology allows for highly precise drilling under the surface without the need for open trenching or disruption to dunes and beaches. Each of the four planned boreholes will be approximately 1,200 meters long, at depths of 20–30 meters below ground level. The work is being carried out by a consortium of Polish contractors: ROMGOS Gwiazdowscy and ZRB Janicki.

- This is a symbolic step for the entire project – connecting the offshore section with the onshore infrastructure, said Ulrik Lange, project director for Baltica 2 at Ørsted. - Using HDD, we can do this in a way that is safe for the environment and virtually invisible from the beach.

Bartosz Fedurek, president of PGE Baltica, added: - This is the least invasive way to install export cables. It does not require beach closures and allows us to carry out the work while preserving the landscape and natural surroundings.

Access maintained, local impact minimized

Public access to the beach remains open via marked pedestrian routes. The developers ask that all visitors follow signage and guidance from site personnel. Activities are coordinated closely with local authorities, and any necessary temporary changes to access or traffic will be communicated in advance.

To reduce noise-related inconvenience for residents and tourists, the project uses carefully selected equipment and construction zones located away from residential areas and the beachfront.

Environmental safeguards in place

Before the drilling began, comprehensive environmental studies were carried out both offshore and onshore. As a result, the cable route was designed to avoid ecologically sensitive areas, including habitats of the smooth snake (Coronella austriaca, a protected species in Poland), and the Lubiatowska Dune, one of the region’s most valuable natural features. The design also takes into account Natura 2000 protected areas.

Qualified environmental supervisors will oversee compliance with environmental regulations throughout construction.

Clean power for 2.5 million homes

Once drilling is completed – expected between late 2025 and early 2026 – installation of the export cables will begin. These will carry electricity generated by the offshore turbines to the national grid. With a planned capacity of 1.5 GW, Baltica 2 will provide enough clean, renewable power for around 2.5 million households, making it a cornerstone of Poland’s offshore energy transformation.

Source: Gazeta Morska · Compiled by: Kamil Kusier

Kamil Kusier executive editor All articles by this author →

Comments (0)

The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.

Nobody has commented on this article yet.

Add a comment

0 comments

Related articles