Prosecutor launches investigation into closure of Siennicki Bridge
The Gdańsk District Prosecutor's Office in Wrzeszcz has launched an investigation into possible abuse of power or failure to fulfil official duties in connection with the decision to close the Siennicki Bridge over the Dead Vistula to traffic – according to a statement received by Gdańsk City Council members, confirmed by local councillor Przemysław Majewski (PiS).
In brief
The Gdańsk-Wrzeszcz District Prosecutor's Office opened an investigation on 2 April 2025 into abuse of powers or dereliction of duty in the decision to close the Siennicki Bridge over the Martwa Wisła. PiS councillors filed the complaint against Gdańsk Mayor Aleksandra Dulkiewicz and her deputy Piotr Borawski on 3 February, and councillor Przemysław Majewski informed PAP about the opening of the investigation. The Siennicki Bridge was closed on 10 January because its abutments were shifting, and the repair is expected to take about two years and cost about 30 million zlotys.
Majewski told PAP that city councillors received a letter on Thursday notifying them of the opening of the proceedings. The investigation concerns the municipal authority’s handling of the closure of the Siennicki Bridge, a key crossing serving Port Island and surrounding districts.
– Earlier, we were questioned by the prosecutor's office about this matter, and now the City Council has received an official notice that the investigation has been initiated – said Majewski, who also provided PAP with a scan of the letter from the prosecutor.
The document states that the investigation was formally launched on April 2, 2025.
Daniel Stenzel, spokesperson for the Gdańsk City Hall, stated on Thursday that the city is fully cooperating with the prosecutor's office.
The motion to initiate proceedings was submitted by PiS councillors on February 3, supported by MP Kacper Płażyński. The announcement came during a press conference held on the same day.
The Siennicki Bridge was closed on January 10 due to severe technical issues. Engineers from the Gdańsk University of Technology found that the abutments of the bridge were shifting, posing a serious risk of collapse. The repair project is expected to take around two years and cost approximately PLN 30 million.
During the earlier press briefing, MP Płażyński argued that city officials had known for over six months that the bridge could be rendered unusable at any moment.
– Yet no steps were taken during that time to prepare for such a scenario. Residents were left in the dark and had no chance to plan their daily routines around the risk – he said.
Councillor Majewski pointed out that the complaint submitted to the prosecutor's office named two individuals: Gdańsk Mayor Aleksandra Dulkiewicz and her deputy Piotr Borawski.
– They are the decision-makers. They had access to the technical evaluations and to an expert report from 2020 – Majewski noted.
In his view, city officials should have ensured proper communication and contingency plans for residents of Port Island before closing the bridge.
In late January 2025, the Gdańsk City Hall published a timeline of actions taken regarding the Siennicki Bridge. The document notes that in April 2024, a new contractor was hired to carry out the investment. A month later, engineers from the Gdańsk University of Technology issued a technical opinion identifying structural shifts in the bridge abutments. They recommended regular monitoring and biweekly inspections.
From May through December 2024, the bridge was monitored on a weekly basis.
The Siennicki Bridge, alongside the cable-stayed bridge and the tunnel under the Dead Vistula, is one of the main access points connecting the districts of Stogi, Przeróbka and Górki Zachodnie with central Gdańsk.
Source: PAP / Gazeta Morska · Compiled by: Kamil Kusier
Related articles
Ports and logistics One bid for Gdynia's Outer Port. MSC wants the 5-billion-zloty terminal, three rivals walked away
Ports and logistics CMA CGM Pantheon in Gdańsk. A success for the port and a bitter lesson about the absence of maritime policy
Ports and logistics CEVA ships a 29-tonne broken Eiffel Tower from Le Havre to Burning Man
Ports and logistics US sinks Iranian tanker in the Gulf of Oman as Hormuz traffic stays at 7 percent
Ports and logistics Maersk to fit a 35 m rotor sail on an 8,700 TEU Lima-class ship in 2027
Ports and logistics Thirty years and 26 hectares. Baltic Hub leases Deepwater and plans a second rail siding
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.