Polish court rejects environmental appeals over Świnoujście container terminal
The Provincial Administrative Court (WSA) in Warsaw has dismissed appeals filed by environmental groups against the environmental permit for the planned deep-water container terminal in Świnoujście. The court ruled that the General Director for Environmental Protection (GDOŚ) complied fully with all legal procedures. The ruling is not final and may be appealed to the Supreme Administrative Court (NSA).
In brief
Complaints by environmental organisations against the environmental decision for the deepwater container terminal in Świnoujście were dismissed by the Provincial Administrative Court in Warsaw. The complaints were filed by the German Bürgerinitiative Lebensraum Vorpommern and the association Zielone Wyspy Świnoujście, and the decision of the General Director for Environmental Protection was issued in February 2025. The terminal is to be built by 2029 and handle vessels up to 400 metres in length, with the cost of the entire project at around 12.5 billion zlotys. The ruling is not final.
Wizualizacja terminala kontenerowego w Świnoujściu / fot. Ministerstwo Infrastruktury
The appeals were lodged by two organizations: Bürgerinitiative Lebensraum Vorpommern, a German NGO from the island of Usedom, and Zielone Wyspy Świnoujście, a Polish ecological group. Their objections focused on potential impacts on protected areas of the Baltic Sea, as well as risks from unexploded ordnance and chemical munitions dating back to World War II.
However, the court found no procedural violations or grounds to annul the decision.
- The GDOŚ conducted all required consultations, including cross-border processes, obtained the necessary expert opinions, and thoroughly addressed all objections raised in the appeals, said presiding judge Anita Wielopolska in the ruling's justification.
She also noted that the investor – the Szczecin and Świnoujście Seaports Authority (ZMPSiŚ) – had supplemented the Environmental Impact Assessment (EIA) as requested, and the German NGO’s input was reflected in the final documentation.
Strategic project for the Baltic region
The container terminal in Świnoujście, part of the planned external port, is one of Poland’s largest maritime infrastructure projects. Scheduled for completion in 2029, it will be capable of handling transoceanic container vessels up to 400 meters long, positioning Świnoujście as a key logistics hub on the Baltic Sea.
Project highlights include:
- A 65-kilometre approach fairway dredged to 17 meters, developed by the Maritime Office in Szczecin,
- Berths capable of simultaneously accommodating two large container ships,
- Full supporting infrastructure, including rail, road, and utility links.
The investment, coordinated by the Polish Ministry of Infrastructure, is valued at approx. PLN 12.5 billion (€2.9 billion), with the terminal itself costing PLN 2.5 billion and the maritime infrastructure approximately PLN 10 billion. Construction is to be undertaken by a Qatari-Belgian consortium.
Legal proceedings continue
The February 2025 environmental decision issued by GDOŚ follows a complex administrative path. An earlier permit issued by the regional directorate (RDOŚ Szczecin) was overturned in 2023 following legal challenges. GDOŚ then took over the appeal process and required a revised and extended environmental report from the investor.
In parallel, the city of Świnoujście in 2024 filed a separate appeal against the terminal’s location permit issued by the West Pomeranian voivode. Moreover, Bürgerinitiative Lebensraum Vorpommern requested suspension of the environmental permit's enforcement. On July 21, the court temporarily granted this suspension, but the investor has appealed the decision.
Despite ongoing proceedings, the port authority remains committed to the project.
- This is an important milestone. The project will continue as planned. Construction will move forward, said ZMPSiŚ president Jarosław Siergiej following the hearing.
Government downplays safety concerns
Poland’s deputy infrastructure minister Arkadiusz Marchewka responded to claims raised by the German NGO regarding seabed hazards, including chemical weapons and munitions from WWII.
- The site has been fully surveyed. Should any ordnance be found, the Polish Navy will handle it professionally. The objections raised are, in our view, exaggerated and lack substantive basis, he said.
The Świnoujście deep-water container terminal is set to become a strategic gateway for transoceanic trade in the Baltic region. With the Warsaw court’s rejection of environmental appeals, the project has taken a significant step toward realization—bolstering Poland’s ambitions as a maritime logistics leader in Northern Europe.
Source: Gazeta Morska / PAP · Compiled by: Kamil Kusier
Related articles
Shipbuilding industry Poland christens ro-pax ferry Bursztyn Unity in Szczecin on Independence Day. Ystad service starts 18 November
Energy and offshore Orlen Neptun deploys V-LiDAR buoys at Baltic West ahead of Poland's 2027 offshore wind auction
Energy and offshore Equinor takes over Bałtyk 2 and 3 O&M base in Łeba. Port to serve 1.44 GW of offshore wind for 30 years
Navy and defence Port Gdański Eksploatacja secures NATO NCAGE code. Gdańsk port company lines up for defence tenders
Shipbuilding industry Ex-Enterprise towed to Mobile under $418.5m contract. Test case for Nimitz-class disposal begins
Energy and offshore Energa renames Gdańsk gas plant company as foundations for 6,000-tonne turbine and boiler are laid
Comments (0)
The discussion is moderated by the editors: a comment appears after review. Your e-mail address is not published.
Nobody has commented on this article yet.