ORLEN Neptun prepares service port for Baltic West Offshore Wind Farm
ORLEN Neptun has signed a reservation agreement with the Port Authority of Kołobrzeg, securing an area in the port to prepare a service hub for the next ORLEN Group offshore wind farm under the second phase of offshore wind energy development – Baltic West.
business power engineering investments offshore west pomerania ports news24 january 2026 | 11:17 | Source: Gazeta Morska | Prepared by: Kamil Kusier | Print

fot. Port Kołobrzeg
- The closer collaboration formalized through the reservation agreement will enable analyses and the preparation of pre-project documentation. This will allow us to apply solutions best suited to the implementation of the Baltic West offshore wind farm. The experience gained in this process may contribute to developing the port’s infrastructure potential for future OWE projects in this part of the Baltic Sea, emphasized ORLEN Neptun.
The Port of Kołobrzeg is the closest port to the project location among all available ports in this part of the Baltic. “Due to its convenient location, Kołobrzeg is the optimal site for servicing this offshore wind farm. Currently, the port meets infrastructure requirements for supporting offshore wind farms with CTV vessels along the central coast,” the company added.
The Baltic West project comprises four concessions in the Ławica Odrzańska area: 14.E.1 and 14.E.2 owned by subsidiaries of Energa Wytwarzanie, and 14.E.3 and 14.E.4 owned by ORLEN Neptun subsidiaries. It is the second project after Baltic East under ORLEN Group’s second phase of offshore wind energy development. The planned total installed capacity of Baltic West is approximately 4 GW, providing clean energy to over 5 million households in Poland. All four areas are being prepared to participate in Poland’s offshore wind support scheme, with full project completion planned by 2040.
The projects have permits for constructing or using artificial islands, structures, and devices, as well as preliminary grid connection conditions. In the coming months, ORLEN Neptun plans to conduct a series of site studies, including environmental assessments, wind measurements, and geotechnical investigations.
At the end of 2025, ORLEN Neptun announced the success of its most advanced second-phase OWE project – Baltic East. The project was among the winners of Poland’s first offshore wind auction conducted by the President of the Energy Regulatory Office. This achievement represents a key step toward the development of renewable energy sources and the continuation of building a safe, stable energy system in Poland.
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
comments
Add the first comment
see also
Gdańsk secures PLN 16.5 million to expand Górki Zachodnie marina
Szczecin Maritime University launches tender for PLN 625 million research vessel
PGE Baltica signs letter of intent with Chordata. Turbines to get predictive acoustic monitoring
Bechtel takes over Poland's nuclear plant site. Earthworks begin in Choczewo
WB Group moves naval communications from land to sea. FONET-NAVY system reaches more warships
The Maritime Office in Słupsk returns after six years
Thirty years and 26 hectares. Baltic Hub leases Deepwater and plans a second rail siding
Themis nears first flight. The rocket's return manoeuvre is being built in Gdynia
Aquapark Reda after the chemical incident. Sharks, permits and species protection
Good energy returns to the beach in Ustka. Two weeks of free attractions from the PGE Foundation
ADVERTISEMENT
ADVERTISEMENT