Baltic Industrial Group delivers first steel components for Baltica 2 foundations
Baltic Industrial Group (GPB) has completed the first secondary steel components for the Baltica 2 offshore wind farm—Poland’s largest offshore project currently under construction, jointly developed by Ørsted and PGE. The initial batch includes anodic cages and a service vessel berthing platform, which play a critical role in corrosion protection and operational access to turbine and substation foundations.
business power engineering maritime economy investments offshore pomerania tricity news03 december 2025 | 22:46 | Print

fot. Orsted
Key structural elements for long-term offshore resilience
Under the contract, GPB will manufacture and supply 111 anodic cages and 111 service vessel berthing platforms — four for offshore substations and 107 for turbine foundations. These structures ensure safe access for maintenance crews, provide attachment points for safety and firefighting equipment, and safeguard the integrity of the primary steel over decades of exposure at sea.
Production began in late July this year, with completion of the full scope scheduled for mid-August 2026. Manufacturing at GPB’s facilities in Gdańsk strengthens Poland’s offshore supply chain and demonstrates the rapidly expanding capabilities of the national industrial sector.
Milestone demonstrates offshore manufacturing competence
According to Ørsted and PGE representatives, the completion of the first units confirms GPB’s readiness for repeatable, specification-compliant serial production. Precision manufacturing is essential, given the demanding quality standards and environmental conditions offshore structures must withstand.
The developers emphasize that the involvement of Polish companies is not only a strategic element of the energy transition, but also a strong driver for domestic capability-building, workforce development, and long-term supply chain growth.

Quality assurance and safety at the core
The production process includes welding operations, steel cutting, lifting activities, mechanical finishing, and work at height — all performed under rigorous safety and risk management protocols. Each component undergoes a comprehensive inspection and test plan, with full material traceability and daily supervision by the developers’ representatives. Final inspection is conducted prior to shipment to storage.
Safety remains a core pillar of the collaboration between Ørsted, PGE, and GPB throughout the project lifecycle.
Baltica 2 – a flagship offshore wind project for Poland
Once commissioned in 2027, Baltica 2 will deliver approximately 1.5 GW of clean energy, enough to supply around 2.5 million Polish households. It is a cornerstone of Poland’s offshore wind development and the largest offshore wind farm currently being built in the Baltic Sea region.
Buy us a coffee, and we’ll invest in great maritime journalism! Support Gazeta Morska and help us sail forward – click here!
Kamil Kusier
redaktor naczelny
comments
Add the first comment
see also
MSC wants to buy Meyer Werft. The sole bidder in Gdynia is negotiating to take over the German yard
Crist has started Huragan's bow. The third Miecznik frigate is being built in two Gdynia yards at once
WB Group and Kongsberg to build unmanned maritime systems in Gdynia. Radmor grows to 2,000 jobs
76 turbines stand in the Baltic. Baltic Power completes its offshore campaign and enters commissioning
A 1,112-metre pier into the sea at Lubiatowo has its environmental decision. Reactor vessels will arrive by sea
A third companion for Leviathan. Indratus, the former Game Changer, leaves Oceanco after a refit
Italy uses its 95-year-old tall ship to promote the nation. Poland has Dar Młodzieży and a quarrel over a quay
President signs the fuel windfall tax and demands cuts now. What it means for fishermen and ports
One bid for Gdynia's Outer Port. MSC wants the 5-billion-zloty terminal, three rivals walked away
Batavia goes ashore. The Dutch show what to do with a ship no longer worth keeping afloat
ADVERTISEMENT
ADVERTISEMENT