Poland's first nuclear plant: site works cover 330 hectares, first orders reach Polish suppliers
Two permit applications are with the authorities, earthworks cover more than 330 hectares on the Baltic coast and the first component orders have reached Polish fabricators. Against that background Polskie Elektrownie Jądrowe (PEJ), the state-owned investor in Poland's first nuclear power plant, issued a statement on 21 November responding to media reports about the cost of its cooperation with the Westinghouse-Bechtel consortium. The company says contractor expenses are verified rather than accepted automatically and that its contracts were negotiated with the state's legal counsel at the table.
In brief
PEJ responds to reports on the cost of Poland's first nuclear plant as site works continue in Pomerania and long-lead orders reach Polish suppliers.
Where the project stands
The plant is being built at the Lubiatowo-Kopalino site in the municipality of Choczewo, Pomerania. It will consist of three Westinghouse AP1000 units with a combined capacity of about 3,750 MW. First nuclear concrete is planned for 2028 and the first unit is due to start operating in 2036.
Bechtel has managed the site since 5 August 2026 and is carrying out the second stage of preparatory works with Polish subcontractors. The scope includes levelling and embankments, about 16 km of temporary roads, 6 km of drainage ditches and the construction base with warehouses, workshops and laydown areas. Budimex is responsible for the earthworks and Polimex Mostostal will build the module assembly buildings next to the site. Detailed geological surveys are continuing onshore and offshore.
Two applications that set the timetable
On 30 October PEJ applied to the Pomeranian Voivode for a construction permit covering Early Works. This stage includes deep excavations for the three reactors and the securing of their walls, a retention reservoir, internal roads and launch shafts for the tunnel boring machine that will build the cooling water system. Seawater intake and discharge pipelines will run beneath the beach and the Baltic seabed using a trenchless method. The company expects the permit in 2027.
The application for the nuclear construction licence was submitted to the President of the National Atomic Energy Agency on 31 March 2026. With its annexes it runs to more than 40,000 pages. PEJ expects the regulator's decision in 2028.
State counsel at the negotiating table
Design and preparatory work is carried out under the Engineering Development Agreement (EDA), in force since 2025. In a position published on 21 November, after media reports about the cost of cooperation with the consortium, PEJ set out how that agreement was reached and how contractor costs are settled.
– It is not true that the EDA was signed in the wording proposed by the American companies. Its conclusion was preceded by many months of negotiations, in which PEJ has worked closely with the General Counsel to the Republic of Poland since August 2024 – Polskie Elektrownie Jądrowe stated.
The General Counsel, the state body responsible for protecting the interests of the State Treasury, also supports the company in negotiating the main engineering, procurement and construction (EPC) contract, together with law firms experienced in the international nuclear sector. Those negotiations have been under way since August 2025.
Every contractor expense is checked
The second issue is how the consortium's costs are settled. PEJ says expenses claimed by its American partners are reviewed before they are paid, and that the project is subject to multi-level supervision and regular reporting to the company and the government.
– It is also not true that expenses submitted by contractors were automatically accepted by the Company. All costs are subject to detailed verification of their connection with the project, their justification and proper documentation. The mere submission of an expense by a contractor does not oblige PEJ to cover it – the company said.
PEJ added that citing individual cost items without their full contractual and project context may lead to wrong conclusions about how settlements between the parties work. The company also noted that the irregularities identified by the Supreme Audit Office in its review of the nuclear programme for 2020-2024 concerned an earlier agreement from 2023 that is no longer in force, and that the audit's recommendations have been implemented.
– The overriding goal of PEJ remains the timely, safe and cost-effective delivery of the first nuclear power plant in Poland – Polskie Elektrownie Jądrowe declared.

Long-lead items and Polish suppliers
The company does not confirm reports of a delay to an agreement on advance payments for long-lead items. In October PEJ instructed Westinghouse to begin procuring these components for the first unit. The order covers six elements of the nuclear island, including the reactor containment vessel and related structural modules.
In the same month Westinghouse placed preliminary orders with four Polish suppliers: Energomontaż-Północ Gdynia, FAMAK, Mostostal Kielce and Mostostal Kraków. On 19 November, at the seventh ministerial meeting of the Partnership for Transatlantic Energy Cooperation, PEJ and the consortium signed a letter of intent to extend the EDA to a further batch of long-lead items. Some of these components will be manufactured in Japan and the United States, and the American partners will support PEJ in talks with export credit agencies on financing linked to the deliveries.
EPC contract expected next year
In September PEJ and Westinghouse-Bechtel agreed the main commercial terms of the EPC contract. PEJ's chief executive, Marek Woszczyk, has said the aim is to close negotiations by the end of this year and sign the contract next year, once corporate approvals are in place on both sides.
The detention in early November of the head of Westinghouse's Polish subsidiary, in an investigation into a coal-fired unit project at Ostrołęka, has not affected the talks, according to Poland's energy minister, Miłosz Motyka. PEJ also points to the European Commission's approval of state aid for the project as one of the steps already secured.
Will Poland finally get its nuclear power plant? Machines are at work on the Pomeranian coast, the applications are filed and the first orders are with Polish plants. This is Poland's project, so let us hope the answer is yes.
Source: Gazeta Morska