Dar Młodzieży successor bids exceed budget by PLN 86-157 million. What Freire, CRIST and Wulkan offered
All three shipyards bidding in Gdynia Maritime University's tender for the successor to Dar Młodzieży have offered the same delivery period, 46 months from contract signature, and the same 24-month warranty. They differ in price, experience and partners. Spain's Freire is the cheapest and leads the preliminary evaluation with around 100 points, followed by Gdynia-based CRIST with 86 and Szczecin's Wulkan shipyard with 81. However, every bid exceeds the university's budget by between 25 and 46 per cent.
In brief
Bids for the successor to Dar Młodzieży exceed Gdynia Maritime University's budget by PLN 86-157 million. Freire, CRIST and Wulkan all offered 46 months' delivery and a 24-month warranty. Spain's Freire, builder of KRI Bima Suci, leads, while Wulkan is working with designer Zygmunt Choreń.
Gdynia Maritime University (UMG) opened the bids on 24 November in a repeated design-and-build tender. The university has allocated PLN 340 million gross to the contract and received a first tranche of PLN 131 million in March 2026. It is now verifying the bidders' documentation and awaiting a government decision on funding.
Prices and scoring
The lowest price, PLN 426,250,350 gross, came from Construcciones Navales P. Freire of Vigo, exceeding the budget by PLN 86.3 million, or around 25 per cent. Gdynia-based CRIST S.A. priced the contract at PLN 452,622,780 gross, PLN 112.6 million (33 per cent) over budget. The most expensive bid, PLN 497,271,780 gross, was submitted by Stocznia Szczecińska "Wulkan", PLN 157.3 million or 46 per cent above the budget.
Price accounts for 60 per cent of the evaluation, with the remaining criteria including experience in designing and building sailing ships. In the preliminary evaluation, Freire scored around 100 points, CRIST 86 and Wulkan 81. As all bidders offered identical delivery and warranty terms, the ranking was decided by price and demonstrated experience.
– All the bids submitted are higher than the amount allocated – noted UMG Rector Professor Adam Weintrit.
Freire: cheapest and the only one with a tall ship to its name
Of the three bidders, only the Spanish shipyard demonstrated experience in building sailing ships in its bid. The family-owned Construcciones Navales P. Freire has operated in Vigo since 1895 and builds vessels of up to 155 metres in length, including research, hydrographic and patrol ships. Its deliveries include the Belgian research vessel RV Belgica and Falkor (too) for the Schmidt Ocean Institute.
Freire's key reference is the sail training ship KRI Bima Suci, delivered to the Indonesian Navy in September 2017. The three-masted vessel is 110 metres long, carries 3,350 square metres of sail and accommodates 200 people, including 120 cadets. These parameters are very close to those planned for Dar Młodzieży's successor, giving the Vigo yard an advantage in the non-price criteria.
CRIST: the Gdynia yard in second place
Gdynia-based CRIST S.A. submitted the second-lowest bid and ranks second in the preliminary evaluation. The shipyard has operated since 1990 and in 2009 acquired the production facilities of the former Gdynia Shipyard. It builds ferries, offshore vessels and steel structures, and in April 2026 won a tender to design and build an electric ferry for Estonia.
CRIST cooperates with Gdynia Maritime University on student internships and practical classes. However, it did not demonstrate experience in building sailing ships in its bid and has not yet publicly disclosed details of its proposal, including any design partners.
Wulkan: the most expensive bid, with Dar Młodzieży's designer on board
Stocznia Szczecińska "Wulkan" submitted the most expensive bid but is the only bidder to have publicly revealed the team with which it plans to build the ship. Its partners include naval architect Zygmunt Choreń, the designer of Dar Młodzieży, and 3Oceans, the company of Piotr Kulczycki, owner of the brig Fryderyk Chopin. The rigging is to be designed and manufactured together with specialist firms from Poland and Europe.
– Our bid includes components and equipment of the highest quality, because this sailing ship is to serve the university for decades and at the same time be a source of pride for Gdynia, Szczecin and the whole of Poland – Stocznia Szczecińska "Wulkan" said.
Wulkan is currently building, among other projects, a floating dock for the Gryfia shipyard, a large part of the hull of the Polish Navy rescue ship ORP Ratownik, and a specialised vessel for Szczecin's maritime university. The shipyard says it also wants to build Dar Młodzieży's successor in Szczecin.
A 169-person frigate echoing Dar Pomorza
Whichever yard wins, the new sailing ship is to be a three-masted frigate around 112 metres long (compared with Dar Młodzieży's 108.8 metres) and around 15 metres wide, with hybrid propulsion of around 1,300 kW. It will accommodate 169 people, including 33 crew. Its sail area will be at least 3,300 square metres, compared with 3,015 on Dar Młodzieży, and its masts will reach 58.4 metres, compared with around 49.5 metres. The ship's silhouette is to echo that of Dar Pomorza.
With the 46-month delivery period offered by the shipyards and a contract signed in early 2027, the new ship would be handed over to the university at the end of 2030. Dar Młodzieży, launched in 1981 at the Gdańsk Shipyard, has trained future merchant navy officers for more than four decades.
Decision due in December
The shipyards have until 7 December to supplement their documents. A decision on the tender's future may be announced on 8 December, UMG's university day, when ministry representatives are expected to visit. The university is awaiting confirmation of whether funding will be increased, whether the procedure can continue, or whether it will have to be repeated.
If additional funding is secured and the tender is completed without appeals, the Rector hopes to sign the contract in January or February 2027 and begin construction in February. Three bids, including two from Polish shipyards, show that building a new sail training ship for Poland is within reach and that there is enough competition to give the university a genuine choice.
Source: Gazeta Morska